What is the first thing to verify before rigging a sling to a load?

  1. Inspect for visible damage

  2. Check the rated load capacity for the rope or sling

  3. Ensure proper weight distribution

  4. Confirm the type of load

The correct answer is: Check the rated load capacity for the rope or sling

Before rigging a sling to a load, it is crucial to check the rated load capacity for the rope or sling. This step is fundamental because every lifting device has a maximum load that it can safely handle. Knowing the rated load capacity ensures that the selected sling or rigging equipment is suitable for the specific load to be lifted, which is essential for preventing equipment failure or accidents during the lifting process. Understanding the rated load capacity helps in selecting the right type and size of sling, ensuring safety and compliance with industry standards. Failure to confirm this information can lead to severe consequences, including equipment damage, injury, or loss of life. Therefore, verifying the rated load capacity is a non-negotiable step in the rigging process.